  直流架空线路与交流架空线路相比,在机械结构的设计和计算方面,并没有显著差别。但在电气方面,则具有许多不同的特点,需要进行专门研究。对于特高压直流输电线路的建设,尤其需要重视以下三个方面的研究:

  1. 电晕效应

  直流输电线路在正常运行情况下允许导线发生一定程度的电晕放电,由此将会产生电晕损失、电场效应、无线电干扰和可听噪声等,导致直流输电的运行损耗和环境影响。特高压工程由于电压高,如果设计不当,其电晕效应可能会比超高压工程的更大。通过对特高压直流电晕特性的研究,合理选择导线型式和绝缘子串、金具组装型式,降低电晕效应,减少运行损耗和对环境的影响。

  2. 绝缘配合

  直流输电工程的绝缘配合对工程的投资和运行水平有极大影响。由于直流输电的“静电吸尘效应”,绝缘子的积污和污闪特性与交流的有很大不同,由此引起的污秽放电比交流的更为严重,合理选择直流线路的绝缘配合对于提高运行水平非常重要。由于特高压直流输电在世界上尚属首例,国内外现有的试验数据和研究成果十分有限,因此有必要对特高压直流输电的绝缘配合问题进行深入的研究。

  3. 电磁环境影响

  采用特高压直流输电,对于实现更大范围的资源优化配置,提高输电走廊的利用率和保护环境,无疑具有十分重要的意义。但与超高压工程相比,特高压直流输电工程具有电压高、导线大、铁塔高、单回线路走廊宽等特点,其电磁环境与±500千伏直流线路的有一定差别,由此带来的环境影响必然受到社会各界的关注。同时,特高压直流工程的电磁环境与导线型式、架线高度等密切相关。因此,认真研究特高压直流输电的电磁环境影响,对于工程建设满足环境保护要求和降低造价至关重要。

RELATED INFORMATION
2023-01-13

In the evaluation of "2021 Henan Province Construction Industry Integrity Model Enterprise and Excellent Project Manager" by the Henan Provincial Construction Industry Association in 2022, our company's Li Haijun, Wang Guojing, and Zhang Shuaibing were awarded the honorary title of "Excellent Project Manager of Henan Province Construction Industry Enterprise". With years of experience and dedication, their hearts and hands are united. With the clearest original intention and the most tenacious attitude, they have tempered themselves and created exquisite products. Li Haijun, a mid-level engineer in the second level construction division, serves as the following

2022-11-23

There is a kind of determination called 'united as one, overcome difficulties together', and a kind of dedication called 'sacrifice small homes, take care of everyone'. The sudden COVID-19 swept through Zhengzhou. For a moment, shopping malls, residential areas, office spaces, communities, etc. were all "locked down". Although the city slowed down, the operation and maintenance of power equipment could not stop for even a minute. Botai Power's operation and maintenance personnel have been on the front line 24 hours a day since the outbreak of the epidemic, demonstrating their responsibility and dedication through actions, silently dedicating themselves to fulfilling their original mission and becoming a part of the epidemic

2022-09-07

It is said that the gaps between fingers are too wide, time is too thin, and I have not yet realized that the three summers have ended. The time has already turned into a new autumn, although there are still frequent hot waves rolling, the footsteps of autumn have arrived at the doorstep. Let's follow the gentle breeze, step on fallen leaves, slow down the pace of life, and enjoy the beautiful parent-child time of autumn. All the beauty comes as scheduled for parent-child team building. In order to help everyone relax, release stress, and enhance communication and exchange among colleagues amidst busy work and life, on September 3rd, Botai Electric organized the "Unity and Happiness" event

Copyright © 2018-2026 hnbotai.com Henan Botai Electric Power Engineering Co., Ltd. All Rights Reserved Support:hnwd.net